C3 Construction Update

February 2024

Upstairs Counseling Offices

Our upstairs construction project includes five counseling offices, a waiting area and a restroom. This ‘C3 Counseling’ area will be just to the left of the elevator. Everything has been framed in and sheetrocked! We are getting ready to add electrical, plumbing and windows.

Elevator & Stairs

To the left as you enter the lobby (behind a plywood wall), we are installing an elevator!  The shaft is complete and the roof has been modified to accommodate the new elevator, which is in production and scheduled for completion mid-May.  There will be an emergency exit and staircase adjacent to the elevator and a new Safety office between the elevator and Starting Point Room.

A staircase to the new second floor is being crafted in the rear of the lobby by the coffee area. This stairway is currently protected by a locked door.  When the second floor is cleared for occupancy, this door will be removed and the staircase will be visible.

what are C3 services like?

In all three venues you will find a live band that will lead us in a few songs (you can sing along or just listen). A pastor will give a message that is relevant to your life. He will speak from either the East or West venue and he’ll be live streamed into the other venues. You can take notes in your program or on our app or you can just sit and listen! Connection cards, tithes and offerings are put in boxes at the back of our venues or submitted online or on our app.

…all in about 60 minutes!

Come on In!

East & West Venue

8:45 | 10:00 | 11:15

north venue

8:45

download
our app

MyChurch by Pushpay
(Keyword C3TC App)
 

google play

find us on social media

Contact us

Phone

509-627-2055

Address

150 Gage Boulevard
Richland, WA, 99352

Come on In!

East & West Venue

8:45 | 10:00 | 11:15

north venue

8:45

find us on social media

download our app

Contact us

Phone

509-627-2055

Address

150 Gage Boulevard
Richland, WA, 99352